Performing Arts Center is facing more delays
By OSCAR CORRAL
The Miami Herald
March 13, 2004
With construction costs threatening to spiral ''out of control,'' the Performing Arts Center's completion date has been pushed back about another six months to the summer of 2006.
Change orders from the builders requesting more money are pouring into Miami-Dade County at the rate of $1 million a week, Gail Thompson, project director for the PAC, said at a meeting this week. County officials fear cost overruns could reach close to $100 million.
County commissioners are outraged.